How to access Task object via XML worksheet
For Task, you can use XML request for the following:
- Inserting Tasks
- Updating Tasks
- Deleting Tasks
- Performing Actions for Tasks
Task
Inserting Tasks
Here is an example XML request to add a new Task in TeamConnect via XML worksheet:
<TeamConnectRequest>
<Authentication>
<Username>george</Username>
<Password>password</Password>
</Authentication>
<Task op="insert">
<Task op="insert">
<PriorityIID>1</PriorityIID>
<ShortDescription>Review Policy</ShortDescription>
<DueOn>2005-07-15</DueOn>
<StartOn>2005-04-27</StartOn>
<EstimatedHours>5</EstimatedHours>
<WorkStatusIID>2</WorkStatusIID>
<CompletedPercent>25</CompletedPercent>
<DefaultCategory>TASK_LOEV</DefaultCategory>
<ActivityItem>ACTI_BILL</ActivityItem>
<Project keymap="NumberString">AP-03211</Project>
<Contact keymap="SsOrTaxNumberString">562-35-3251</Contact>
<ChangeAssignee>
<User>Charlotte</User>
<AssignedOn>2005-06-14T06:30</AssignedOn>
</ChangeAssignee>
<RateAmount>75</RateAmount>
<ActualHours>5</ActualHours>
<TotalAmount>375</TotalAmount>
</Task>
</TeamConnectRequest>
Updating Tasks
Here is an example XML request to update a Task in TeamConnect via XML worksheet:
<TeamConnectRequest>
<Authentication>
<Username>george</Username>
<Password>password</Password>
</Authentication>
<Task op="update" ShortDescription="Review Policy">
<WorkStatusIID>3</WorkStatusIID>
<CompletedPercent>100</CompletedPercent>
<CompletedOn>2005-07-25</CompletedOn>
<ActualHours>7</ActualHours>
<ChangeAssignee>
<User>jane</User>
<AssignedOn>2005-06-18T18:21</AssignedOn>
</ChangeAssignee>
<ChangeAssignee>
<User>jake</User>
<AssignedOn>2005-07-02</AssignedOn>
</ChangeAssignee>
</Task>
</TeamConnectRequest>
Deleting Tasks
Here is an example XML request to delete an Task in TeamConnect via XML worksheet:
NOTE: You can only delete voided tasks.
<TeamConnectRequest>
<Authentication>
<Username>george</Username>
<Password>password</Password>
</Authentication>
<Task op="delete" ShortDescription="Review Policy" />
</TeamConnectRequest>
Performing Actions for Tasks
Reassigning Tasks
Here is an example XML request to Reassigning Tasks in TeamConnect via XML worksheet:
<TeamConnectRequest>
<Authentication>
<Username>george</Username>
<Password>password</Password>
</Authentication>
<Task op="update" ShortDescription="Review Policy" action="forward:charlotte" />
</TeamConnectRequest>
Posting and Voiding Tasks
Here is an example XML request to Posting and Voiding Tasks in TeamConnect via XML worksheet:
<TeamConnectRequest>
<Authentication>
<Username>george</Username>
<Password>password</Password>
</Authentication>
<Task op="update" ShortDescription="Review Policy" action="postTransaction">
<RateAmount>50</RateAmount>
<ActualHours>125</ActualHours>
<TotalAmount>6250</TotalAmount>
</Task>
<Task op="update" ShortDescription="Review Auto Policy" action="voidTransaction" />