The CMO user can now update the compliance status of multiple Obligations using a single Action. Sometimes a single Action can meet the requirement of multiple Obligations. If a company has multiple obligations and a single action can meet the requirement, the user can link one Obligation Action to update multiple Obligation Compliance Statuses.

Add Obligations to an Action

The following steps help the CMO user to add obligations to an action.

1.      Login to CMO application

2.      Go to Actions.

clipboard_ef5ba09e95d8799ef94324da839709f86.png

3.      Click on any existing Action or create a new Action by clicking on New button.

clipboard_e1a8decccad3c9d49226ceafd690daeab.png

clipboard_ed9ebf6ea4282bab123fe15699628c351.png

4.      Open the desired Action to which obligations must be added.

clipboard_e6edbd689e5fc65aa36b29b858ddf78d4.png

5.      When the user click on ‘Add obligation’ button and the Action is a part of Schedule CMO shows a dialog to select ‘scope’ of scheduled actions to be affected (this dialog doesn’t appear for standalone actions):

clipboard_ed19585e13a977096d62a40513b7387a9.png

6.      Once actions are selected CMO asks the user to create a new obligation or select from existing:

clipboard_e99abe0e249a0d39ee8c4e155fb341e07.png

7.      If the user selects ‘New’ then CMO opens ‘Create Obligation’ dialog. Once the user click on ‘Save’ CMO will link newly created obligation to all selected actions.

8.      If user selects ‘Select Existing’ then CMO opens ‘Select Obligation’ dialog

clipboard_ebdb81ef041eb1e8c4d8862d51e64449e.png

9.      To remove links between obligations and actions the user may select obligations using a checkbox in the grid and then press the ‘Remove Obligation’ button on Obligations section:

clipboard_e5d0a504be329b43e63af9ae608d5e606.png

10.   In this case CMO will show confirmation dialog:

clipboard_e15b8aaed533c58ef692dfcbd9987641d.png

11.   When the user clicks on the ‘Remove Obligation’ button (on Obligations section) without selecting obligations in the grid or when the user uses ‘Remove Obligation’ in page menu (top left side of the page) or in context menu CMO asks user to select obligations to be removed (this dialog shows only obligations linked to the action):

clipboard_ed6603994e8f3750bb6520b7b9b997bb1.png

12.   All obligations added / removed to the actions are logged into the action history and can be viewed using History tab on Action View page:

clipboard_eef2c586b283a046fcef80e9d9945425b.png

13.   The Obligations column on Action Register now shows all linked obligations (every obligation is displayed in a separate line):

clipboard_e9793808fca0aca82a7d9a9b5d8188b87.png

Actions Related Changes

Obligations’ section has been added to the Action View page.

clipboard_eb007303aaa6ff9135f889ccdbc2c6e9a.png

The section shows all obligations related to this action (including archived Obligations).

In addition to the left side menu of Action view page and buttons on Obligations section the ‘Add Obligation’ and ‘Remove Obligation’ buttons are available as part of the context menu:

clipboard_e79eff5f610eae6d3ef103a537195d6f5.png

Note:  ‘Remove Obligation’ button is visible only when the Action has linked obligations.

Obligations related changes

A ‘Remove Action’ button has been added to Obligation View page (page menu and Actions section) and to the obligation context menu:

clipboard_e8655b1dc6ca75a7b8bd0d7b2cd2b0a9d.png

clipboard_ec66a67fc483c1f9bb39b5f28807cde16.png

The ‘Remove Action’ button is available only when the Obligation has linked actions.

When the user clicks on the ‘Add Action’ button CMO asks to create new or select existing.

If the user selects ‘New’ CMO shows ‘Create Action’ dialog. CMO will link every created action to the obligation. Note, if a Schedule Action has been created, then all future actions from this Schedule will be linked to this obligation as well (unless user manually unlinks them).

If the user selects ‘Select Existing’ CMO shows a dialog to select actions:

clipboard_e7eefe719872b76b14d1fba59c3b3da72.png

If the user selects an action(s) which is a part of Schedule, then CMO asks to specify scope for the related Schedule (CMO repeats this procedure for every selected Schedule):

clipboard_efe3ebed424ba6e725586979ec46cc9e0.png

The user may use checkboxes (on the grid) to select actions to unlink from the obligation.

clipboard_e0c9d0bd0ed91ab563292cd0311427c4b.png

In this case CMO shows a confirmation dialog:

clipboard_e241eff799a63182d1fcc108d8fe4300c.png

Also, the user may click on the ‘Remove Action’ button without selecting actions. In this case CMO will show a dialog to select actions to unlink:

clipboard_e162f0a1d80fc95bc76c667a50217c15d.png

CMO also shows this dialog when a user select ‘Remove Action’ in the context menu or in the page menu.

If selected action(s) belongs to a Schedule, then CMO asks to specify scope for every Schedule (using the same dialog which has been mentioned before).

All actions added / removed to the obligation are logged into the obligation history and can be viewed using the History tab on the Obligation View page:

clipboard_eff49f22f7e741eba720000cd01cec92a.png